Free Gantt Chart with Dependencies
Finish to Start dependency means that two tasks are related in a way that the first task has to be finished before the second one can be started.
Start to Start dependency means that two tasks are related in a way that the second task can’t start before the first one starts.
Finish to Finish dependency means that two tasks are related in a way that the second task can not finish until the first one finishes.
Start to Finish dependency means that two tasks are related in a way that the second task can not finish until the first one task.
Bitrix24 supports leads and lags for dependencies as well. Since Bitrix24 is available online, it's much easier to use than Gantt in Excel or Google Sheets.
* Please note that the information may have changed since the publication. For current prices and features please visit Bitrix24 pricing page.
* Please note that as of September 2024 some task and project management features are available for free to unlimited users for 15 days only.
Basic Features
- Free for an unlimited number of users
- 5 GB of online storage for free
- Free unlimited projects
- Free unlimited subtasks
- 4 task dependencies
- Multiple Gantt charts
- Unlimited storage
- Cloud & on-premise
- Free mobile PM (iOS and Android)
- Open source code and API
Task Management
Project Management
Time Tracking
Project Collaboration
Projects involve many people and you need collaboration tools that work for your co-workers and external users, such as clients or contractors, alike. Sometimes you need to hold an online meeting or a workgroup discussion or reach someone who's available only via mobile phone. Bitrix24 does all that and more.
No other project management vendor offers you as many social collaboration tools as we do. Your own private social network, employee directory, activity stream, comments, likes, tags, mentions - if you want it, we've got it.
Document Management
Client Management